Major Road Construction Projects

Detour Map of summer road construction projects

Suncrest Drive


Work has begun to reconstruct 3.2 miles of Suncrest Drive from Traverse Ridge Rd. to the Draper City limits. This project has an anticipated completion date of November 1. Two lanes of traffic will be open throughout the duration of the project. Traffic delays should be minimal. The speed limit has been reduced to 30 mph through the construction area. Bikers are encouraged to avoid this area during construction.

Manilla Drive


 A new storm drain line will be installed on Manilla Dr. and the road will be reconstructed from Manti Dr. to Traverse Ridge Rd. Construction will start on May 8 and should be completed by the end of June. This section of Manilla Drive will be open to local traffic only during construction. Motorists are encouraged to use alternate routes to avoid the construction zone.

13800 South Storm Drain


Construction has begun to install a new storm drain line between 300 East and the East Jordan Canal. The project should be completed by the end of May. Traffic through the construction zone will be limited to one lane. One-way traffic through this area will be controlled by temporary traffic signals. Traffic delays are expected, but should be minimal during non-rush hour periods. Motorists are encouraged to avoid this area during the rush hour periods, if possible.

Bangerter Parkway and 13800 South Intersection


This federally funded project will widen the intersection at Bangerter Parkway and 13800 South. New traffic lanes will be added in each of the four legs of the intersection to increase the capacity and traffic flow in all directions. It is anticipated that construction will start in June and be completed by October. The magnitude of the impact to traffic at this intersection are not yet known. More information on this project will be coming soon.

Willow Springs Lane


 Sections of Willow Springs Lane between 700 East and Fort Street will be closed for reconstruction form June 8th to July 14th. Notices of the closures and alternate detours will be provided prior to the closures. More information on this project will be coming soon. 13200 South
It is anticipated that the project to widen and extend 13200 South from the Draper Peak Middle School to Highland Drive will begin in May or June and be completed by the end of September. Traffic delays are expected to be minor during construction. More information on this project will be coming soon.

13200 South


It is anticipated that the project to widen and extend 13200 South from the Draper Peak Middle School to Highland Drive will begin in May or June and be completed by the end of September. Traffic delays are expected to be minor during construction. More information on this project will be coming soon.

Pioneer Road


Pioneer Road from 600 East to 700 East and portions of 700 East (north and south of Pioneer Road) will be widened and curb, gutter and sidewalk will be added through these areas. Alternating closures of Pioneer Road and 700 East may occur throughout the project, with one of the roadways always open through the intersection. Notices of the closures and alternate detours will be provided prior to the closures. It is anticipated that construction will begin in June and be completed by the end of September. More information on this project will be coming soon.


Highland Drive Storm Drain


The existing storm drain in this area is deficient and does not adequately drain storm water when a large storm event occurs.  This project will install main line storm water collection piping for a section of Highland Dr.



Bangerter 600 west header 2

600 West Update - May 11, 2017

***

600 WEST INTERCHANGE OPENING THIS WEEKEND

The new 600 West interchange will open this weekend. Crews will begin to open the on and off-ramps Friday night. It is anticipated that the interchange will be open and fully functional by Saturday morning, May 13.

200 West & Bangerter Intersection Closing THIS WEEKEND

Once the new interchange opens, the 200 West and Bangerter Highway intersection will transition to a right-in right-out access. The following changes will be in place by Saturday morning, May 13:
* A barrier will extend through the middle of the intersection from east to west
* The traffic signals will be removed
* All left-turn movements will be discontinued
* North and southbound movements will be discontinued
* Right-turns will still be accessible

Businesses can be accessed using the 600 West interchange.

IMG 9222

Traffic signals are operational on the new interchange

PROJECT COMPLETION

We are nearing project completion and anticipate wrapping up by mid-June. Thank you for your patience during the project. Please be aware of intermittent lane closures over the next month while crews complete the final details on the project. Please let us know if you have any questions.

Upcoming Work

Installation of median at 200 West intersection
Removal of traffic signals at 200 West intersection
Installation of sidewalks
Landscaping

Ongoing Work

Pouring concrete on 600 West
Constructing curb and gutter on ramps
Signal work on 600 West interchange
Installation of roadside barrier and fencing

Lane Changes on Bangerter

All lanes will be open during peak travel times
6 am to 9 am - Monday to Friday - eastbound
4 pm to 7 pm - Monday to Friday - westbound
12 pm to 4 pm - Saturday - eastbound and westbound (excluding some weekends as noted) Lanes will be reduced by 1 or 2 lanes in each direction during off-peak travel times.

IMG 9223

Landscaping work on the westbound on-ramp

Project Details

A grade separated interchange has been installed at 600 West. Bangerter Highway was raised approximately 12 feet to cross over 600 West.
Right turns will still be accessible at 200 West
The new interchange will tie in to local roads on the north and south sides of Bangerter to improve access to local destinations

What to Expect during construction

Traffic and pedestrian detours
Noise
Vibrations
Dust
Business access will be maintained

Work Hours

Crews will be working 24 hours a day, 7 days a week

IMG 9923

Top: eastbound Bangerter on-ramp, Bottom: pavement marking

Questions or Comments

Please let us know if you have any questions or comments.
Thanks!

600 West Interchange Team
801-649-5476
bangerter600west@utah.gov
udot.utah.gov/bangerter600west

1px