Major Road Construction Projects 2019 / 2020

If you have questions on these projects, please contact Draper City's Engineering office at (801) 576-6369.
Reconstruction of 13800 South from 300 to 980 East We are pleased to announce the reconstruction of 13800 is now complete. This road improvement project added a center turn lane, paved shoulders, curb and gutter, sidewalks, and critical upgrades of utilities such as storm drain, water, and sewer lines. In addition, the project improved safety and access to properties located along the roadway.  There are still a few construction cones up for a few projects to finish driveway connections and landscaping. Questions? Email traffic@draper.ut.us, or call the project hotline at (801) 580-2626. 

11950 South Roadway Extension, 150 East State Street

Draper City, in accordance with the Master Transportation Plan, is extending 11950 South form 150 East to connect to State Street. This road extension will help reduce congestion on 11800 South, at State Street and also at 150 East. The project also includes the relocation of a water line, extension of Storm Drain Facilities and construction of sidewalk, curb, gutter and roadway.  The project is currently under construction but should be completed by the week of December 9-13, 2019.

If you have any questions about this project, please contact the project engineer, Eric Lundell by email or by phone (801) 576-6365.

11950 South

Manilla Dr. Traffic Signal Installation of a traffic signal at Manilla Dr. and Traverse Ridge Road.  This project is under construction.  Expected completion is the end of December, 2019.
Lone Peak Park Widening Project from 11400 South to 12300 South Draper City is currently in the design stage to widen Lone Peak Parkway from 11400 South to 12300 South in 2020. The street widening project will include two travel lanes in each direction, with a center turn lane. Currently, this section of the road has only one travel lane in each direction, with a center turn lane. As part of the project, the city will be adding additional street lights. We anticipate that the construction for this project will start in the spring of 2020.
Bangerter Parkway Mill & Overlay Crews will be resurfacing the asphalt on Bangerter Parkway from 13800 South to Highland Dr. The roadway will be restriped to five lanes. A new traffic signal will be installed at 140th and Bangerter.
Highland Dr. Widening Project Draper City is planning to widen Highland Drive from Traverse Ridge Road west to Minuteman Drive to increase the number of lanes to five.  Two-way traffic will be maintained during the construction.  The project will start in the spring of 2020 and be completed in the fall of 2020.  
Draper Elementary Access Road Draper City and the Canyons School District are working on a second access road to the Draper Elementary School, 1080 E. 12660 South, so that there will be two exit / entry points. Currently, the only access to the school is from the west, off of Fort Street. This single access point limits traffic circulation and flow at the school, and the backup of traffic extends out to and along fort Street. Having one way in and one way out can make it very difficult for emergency vehicles to respond to an emergency.

The new access road will connect the existing 12650 South roadway to Manfield Way (east of the school). This will provide a secondary access point to significantly improve traffic flow during the school’s drop-off and pick-up times as well as during an emergency. Overall, it will provide a safer place for the children to attend and the teachers to work.

The majority of the new roadway will be constructed along the entire north end of the school on property owned by Canyons School District. This will necessitate the construction of an additional parking lot on the school property to replace the existing parking area that will become part of the new roadway. Canyons School District and Draper City will jointly develop an inter-local agreement detailing the responsible costs for each entity.

Construction of this new roadway started this past summer. Due to the scope of this project, the project will be completed next summer (2020). If you have any questions about this project, please contact Eric Lundell, Draper City, at (801) 576-6365.
Oak Vista 1 and 5 Subdivision The city will replace the waterline in this subdivision and reconstruct the pavement. Work will begin in the summer of 2020.
Cephus Road and Vista Station A new traffic signal will be installed at 12560 South 550 West. Work will begin in the summer of 2020.
13490 South and Vista Blvd. A new traffic signal will be installed at 113490 So. and Vista Blvd. Work will begin in the summer of 2020.
1300 East Widening Project 1300 East from Nashi to Wayne's World will be widened from two to three lanes. The project includes adding sidewalks and curb and gutter. The project will begin the summer of 2021.

13490 South and Vista Blvd. A new traffic signal will be installed at 113490 So. and Vista Blvd. Work will begin in the summer of 2020.
13490 South and Vista Blvd. A new traffic signal will be installed at 113490 So. and Vista Blvd. Work will begin in the summer of 2020.